Posada, Italy
One Francis Turbine = 990 kW Installed Power

Project Highlights:

Posada was one of three projects for Mavel undertaken concurrently in Italy for ENEL.  The installation of the turbine took only 40 days.


Project Facts:

Cedrino River, 20 km east of Núoro city, Sardinia, Italy

ENEL Green Power
New

Head = 28 m
Flow = 4 cms  

1 Francis turbine
990 kW

Turbine
Synchronous Generator
Cooling Equipment
Electrical Portion
Supervision of Testing

2006
« back



The view during the assembly phase
at the Italian site of Posada