Fujiyoshida, Japan
One Francis Turbine = 140 kW Installed Power

Project Highlights:

The placement of this turbine was directly in front of Mount Fuji and the second Mavel turbine installed in Japan with Mavel’s partner Himavari N.E. CO., Ltd.  The entire project took only eleven months from signing of the contract in August 2003 to taking over in July 2004.


Project Facts:

Mt. Fuji, Japan

Himawari N.E. CO., Ltd.
Yamaichi Sangyo Co, Ltd.
New

Head = 16.2 m
Flow = 1.06 cms

1 Horizontal Francis turbine FSH450F295
140 kW

Turbine
Asynchronous Generator
Draft tube
Trash rack
Cleaning Machine
Gates
Sensors
Hydraulic Unit
Supervision of Assembly
Testing
Commissioning    

2004
« back


The Mavel Francis turbine being hoisted into
place at the site in front of Mt.Fuji, Japan