| Benesov,
Czech Republic – 27 March 2008- Mavel,
a.s. announced that it was awarded a contract for turbines
and related technology for the Kayalik hydroelectric power
plant ("Kayalik HPP") located in the Erzurum Region of
Turkey. The contract was signed in June 2007 with the
project owner Akua Enerji Uretim A.S.
The Kayalik HPP site has net head of
65 meters and total flow of 10.2 cubic meters per second.
Mavel is supplying two horizontal Francis turbines - each with runner diameter of 800 mm. Mavel's scope also includes generators, control system, lubricating, cooling and hydraulic units.
Commissioning is expected for November
2008. Each turbine generator unit will have installed power
of 3 megawatts for total installed plant capacity of 6 megawatts.
Mavel, a.s. is a Czech Republic-based
manufacturing and engineering company focusing on production
of turbines for hydro-electric power plants from 25 kW to
25+ MW. Over the past 12 years, Mavel and its subsidiary
CKD TurboTechnics, s.r.o. have installed over 300 turbines
at more than 210 sites around the world. |